The second phase of O'Fallon Casting's plant expansion is currently in process. The construction phase of the project should be complete by the end of May 2018.
On the north end of the building, the new tool room and maintenance workshop are up and running. The new tool room is considerably larger than the previous one, with room for expansion and additional pieces of equipment. The new maintenance workshop is larger and more centrally located in the plant. Demolition has begun on the old tool room and maintenance area to clear the way for O'Fallon Casting's new lunch room and security office.
On the south side of the building, the walls and roof are in place on the second phase of the south side expansion. This area will house the new pre-inspection area, heat treat department and the new shipping dock.